NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: July 21st – July 25th, 2025

Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.

Key Phases & Timeline

  • Week of July 21st – July 25th, 2025

  • Work Locations:

    • 13th Street between Adams and Jefferson Streets

    • Adams Street between 14th and 15th Streets

Construction Activities

  • Working on louvers, pump rails, and electrical installation for the pumps at the NWRP on 13th Street between Adams and Jefferson Streets.

  • Installation of curb, curb walls and sidewalk on 15th Street, east of Adams Street.

Traffic Management

  • Adams Street between 13th and 15th Streets will be open to thru traffic one lane going northbound.

  • 15th Street will have traffic going east and westbound from Adams Street to Willow Avenue. Traffic flow will resume as normal.

  • HPD officers will be present at all intersections within work zones.

  • 24/7 no parking signs will be in place on both sides of Adams Street between 14th and 15th Streets.

We appreciate your patience and cooperation as we work to improve our infrastructure.